Activities performed: The Consultants prepared the feasibility study of a 10 MW solar power plant with 7.5 MW/30 MWh battery energy storage system for Moncement Building Materials LLC, Mongolia. The scope of the feasibility study includes the following tasks:
- General information for project implementation
- Energy sector, renewable energy, legal and regulatory environment, and development policy
- Current status and future trends of Mongolia's energy system
- Solar energy in Mongolia and regional resources for project implementation
- Technology selection and planning of solar and battery storage systems
- Modeling and production of solar power plants with battery storage systems
- Project finance and investment analysis
- Operation and technical service of solar power plants with battery storage systems
- Occupational safety and health
- General plan and timeline for project implementation
- General conclusions